No caption
IMG_1804.JPG
Details
Wednesday, December 3, 2025 · 10:35 AM
39.39468, -120.02067· 1661m
Location Context
1 / 5
USGS Topo
No elevation data
FEMA Flood
No flood data
OSM Infra
No address data
USDA Soil
No soil data
USGS Hydro
No hydro data
Apple iPhone 16 Pro
iPhone 16 Pro back triple camera 2.22mm f/2.2
2.220000028611935mmf/2.21/99sISO 100
Flash did not fire, compulsory flash mode
Show all EXIF (43 fields)
ApertureValue2.2750
BrightnessValue5.0528
ColorSpace65535
CompositeImageGeneral Composite Image
ExifImageHeight3024
ExifVersion2.3.2
ExposureCompensation0
ExposureModeAuto
ExposureProgramNormal program
FlashpixVersion1.0
FocalLengthIn35mmFormat14
GPSDateStamp2025:12:03
GPSDestBearing262.9780
GPSDestBearingRefTrue North
GPSHPositioningError5.8541
GPSImgDirection262.9780
GPSImgDirectionRefT
GPSSpeed0.0667
GPSSpeedRefK
GPSTimeStamp18:35:1
HostComputeriPhone 16 Pro
latitude39.3947
LensInfo2.2200, 15.6600, 1.7800, 2.8000
LensMakeApple
longitude-120.0207
MeteringModePattern
ModifyDate2025-12-03T10:35:02.000Z
OffsetTime-08:00
OffsetTimeDigitized-08:00
OffsetTimeOriginal-08:00
ResolutionUnitinches
SceneCaptureTypeStandard
SceneTypeDirectly photographed
SensingMethodOne-chip color area sensor
ShutterSpeedValue6.6325
Software26.1
SubjectArea{"0":2002,"1":1511,"2":2218,"3":1328}
SubSecTimeDigitized138
SubSecTimeOriginal138
WhiteBalanceAuto
XResolution72
YCbCrPositioning1
YResolution72
AI Analysis
A worker in high-visibility clothing is compacting soil at the base of an excavation site. Visible equipment includes an excavator in the background and a compaction tool being used by the worker. Surrounding the site are soil embankments and a building on the right. The scene is outdoors with some trees in the background.
site-grading
exposed soil and embankment daylight conditions clear access with adjacent building
Worker is wearing PPE, including hard hat and high-visibility vest; no additional safety controls visible in frame.
Equipment & Materials
AI Tags
Analyzed Apr 21, 2026
Nearby Photos
1m
excavation
excavationtrench
excavator
1m
trenching
pipe-installationtrenching
soil
2m
electrical
electrical-installationcable-management
electrical-panels
2m
excavation
excavationsite-preparation
compactor
2m
other
roofing-preparationroof-surface-work
plywood
2m
other
roof-inspectioncondition-assessment
3m
survey layout
surveyinglayout
level rod
4m
other
material-stagingmarking
logs
4m
paving surface restoration
surface-markingsfirewood
wood
4m
inspection documentation
roof-inspectionvisual-assessment
stacked-firewood