/WEST/SIERRA CENTER UNDERGROUND UTILITY WORK
487active
All Reports

4 photos at this spot

4 photos · 4 analyzed 39.32609, -120.20219 Mar 11, 2026 · 5:27 AM

85%

completion

First

Oct 23, 2025

48 days

Last

Dec 10, 2025

Over the 48 days, a construction site progressed from initial groundwork to the near completion of a pipeline installation. The site started with access to underground cables and ended with the area being graded, indicating that surface restoration is occurring.

Construction Milestones4 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

Underground cables are visible in a partially open access point.

Current Condition

The ground has been backfilled and leveled with workers compacting the surface.

Timeline

Initial Groundwork

Oct 23, 2025

Access to underground cables was established.

Excavation

Dec 4, 2025

Trench excavation clearly visible with workers preparing the area.

Pipe Installation

Dec 8, 2025

Pipe is clearly laid within the trench with fittings visible.

Backfill Completion

Dec 10, 2025

Backfill is in progress with surface compaction underway.

Work Types Observed

excavationpipe installationbackfillinggrading

Next Steps

Complete surface finishing, monitor for settling, and prepare for potential paving or landscaping.