60%
completion
First
Dec 9, 2025
5 days
Last
Dec 14, 2025
Over the five-day period, significant progress was made with trenching and installation of infrastructure as pipes were laid and covered. The area was actively excavated, with backfilling and surface preparation visible towards the end of the series.
Start Condition
The site shows initial trenching with pipes starting to be laid along the trench.
Current Condition
The site shows multiple pipes laid, some backfilled with initial surface leveling carried out.
Initial Trenching
Dec 9, 2025
Trenching started, and pipes prepared for installation.
Excavation in Progress
Dec 13, 2025
Large-scale excavation with machinery visible.
Pipe Installed
Dec 14, 2025
Pipes laid in trench with workers securing them.
Backfilling Begins
Dec 14, 2025
Trench partially backfilled with some leveling.
Complete backfilling the trenches, finalize leveling, and prepare for any surface finishing or additional installations.
12/9/25
12/9/25
12/13/25
12/13/25
12/13/25
12/13/25
12/14/25
12/14/25
12/14/25
12/14/25
12/14/25
12/14/25
12/14/25