85%
completion
First
Nov 3, 2025
38 days
Last
Dec 11, 2025
Over the 38-day period, the site saw significant progress, including trench excavation, pipe installation, and preliminary backfilling. By the end, structural elements are in place, signifying near completion of underground work.
Start Condition
Initial excavation began with a small trench cut in a paved area.
Current Condition
Site prepared with compacted ground, multiple pipes are installed with surrounding fill nearing completion.
Excavation Begin
Nov 3, 2025
Initial ground breaking and excavation begins with trench cut visible.
Trench Completion
Nov 4, 2025
Trench fully dug to grade and ready for pipe installation.
Pipe Installed
Nov 4, 2025
Main pipe and valve are installed within the trench.
Backfill Partial
Nov 6, 2025
Some backfilling around installed pipes complete, but not final.
Complete backfilling, compact the soil, and prepare the site for final grading.
Ensure proper compaction to prevent future settlement issues.
11/3/25
11/3/25
11/4/25
11/4/25
11/4/25
11/4/25
11/4/25
11/6/25
11/6/25
11/6/25
11/6/25
11/7/25
11/7/25
11/7/25
11/11/25
11/11/25
11/11/25
12/11/25
12/11/25