/FLORISTON FILTRATION PROJECT
3,076active
All Reports

20 photos at this spot

20 photos · 10 analyzed 39.39116, -120.02133 Mar 14, 2026 · 2:14 AM

60%

completion

First

Mar 4, 2025

331 days

Last

Jan 29, 2026

The site transitioned from initial clearing to significant infrastructure development, including earthmoving, grading, and partial tank construction. Final site grading remains to be completed.

Construction Milestones1 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

The site appears to be initially cleared with exposed ground and some vegetation removal.

Current Condition

The area shows substantial earthmoving with built-up areas and leftover construction materials, yet to be fully leveled.

Timeline

Initial Site Clearing

Mar 4, 2025

Vegetation has been removed; groundwork is visible.

Erosion Control Setup

Mar 4, 2025

Erosion control measures, such as straw wattles, are in place.

Heavy Equipment Arrived

Mar 11, 2025

Large construction machinery is on site, indicating preparation for major earthmoving.

Grade Preparation

Mar 11, 2025

Site appears to be graded with stockpiles of material.

Construction Material Delivery

Mar 21, 2025

Concrete tank sections and other materials onsite, indicating start of tank assembly.

Tank Assembly Begun

Mar 21, 2025

Large sections of a tank structure are being assembled.

Work Types Observed

site clearingerosion controlearthmovinggradingtank assembly

Next Steps

Complete tank installation, finish grading the site, and perform site cleanup.

Photos in this Report (20)

3/4/25

3/4/25

3/11/25

3/11/25

3/11/25

3/11/25

3/21/25

3/21/25

3/24/25

3/24/25

3/27/25

4/11/25

5/6/25

5/8/25

5/9/25

5/15/25

6/5/25

10/14/25

10/14/25

1/29/26