60%
completion
First
Mar 4, 2025
331 days
Last
Jan 29, 2026
The site transitioned from initial clearing to significant infrastructure development, including earthmoving, grading, and partial tank construction. Final site grading remains to be completed.
Start Condition
The site appears to be initially cleared with exposed ground and some vegetation removal.
Current Condition
The area shows substantial earthmoving with built-up areas and leftover construction materials, yet to be fully leveled.
Initial Site Clearing
Mar 4, 2025
Vegetation has been removed; groundwork is visible.
Erosion Control Setup
Mar 4, 2025
Erosion control measures, such as straw wattles, are in place.
Heavy Equipment Arrived
Mar 11, 2025
Large construction machinery is on site, indicating preparation for major earthmoving.
Grade Preparation
Mar 11, 2025
Site appears to be graded with stockpiles of material.
Construction Material Delivery
Mar 21, 2025
Concrete tank sections and other materials onsite, indicating start of tank assembly.
Tank Assembly Begun
Mar 21, 2025
Large sections of a tank structure are being assembled.
Complete tank installation, finish grading the site, and perform site cleanup.
3/4/25
3/4/25
3/11/25
3/11/25
3/11/25
3/11/25
3/21/25
3/21/25
3/24/25
3/24/25
3/27/25
4/11/25
5/6/25
5/8/25
5/9/25
5/15/25
6/5/25
10/14/25
10/14/25
1/29/26