/FLORISTON FILTRATION PROJECT
3,076active
All Reports

20 photos at this spot

20 photos · 10 analyzed 39.39475, -120.02265 Mar 12, 2026 · 1:32 AM

60%

completion

First

Apr 7, 2025

294 days

Last

Jan 26, 2026

The construction project involved trenching and pipe installation along a roadwork site over approximately 294 days. Visible progress includes excavation, pipe installation, and site preparation, indicating significant infrastructure upgrades.

Construction Milestones2 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

An undisturbed road surface with markings indicating planned work, seen in the first photo.

Current Condition

An open trench with visible pipes installed, surrounded by traffic cones for safety.

Timeline

Marked Site

Apr 7, 2025

The road was marked for upcoming work.

Excavation Begins

Aug 4, 2025

Excavation equipment is seen removing a large rock along the roadway.

Trenching Ongoing

Aug 5, 2025

Active trench digging is underway.

Pipe Installation

Aug 5, 2025

Pipes are visible laid within the trench.

Work Types Observed

excavationtrenchingpipe installation

Next Steps

Complete trenching to the full extent, finalize pipe installation, proceed with backfilling and surface restoration.

Photos in this Report (20)

4/7/25

4/7/25

8/4/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/5/25

8/6/25

8/7/25

8/7/25

8/22/25

9/4/25

1/26/26