60%
completion
First
Apr 7, 2025
294 days
Last
Jan 26, 2026
The construction project involved trenching and pipe installation along a roadwork site over approximately 294 days. Visible progress includes excavation, pipe installation, and site preparation, indicating significant infrastructure upgrades.
Start Condition
An undisturbed road surface with markings indicating planned work, seen in the first photo.
Current Condition
An open trench with visible pipes installed, surrounded by traffic cones for safety.
Marked Site
Apr 7, 2025
The road was marked for upcoming work.
Excavation Begins
Aug 4, 2025
Excavation equipment is seen removing a large rock along the roadway.
Trenching Ongoing
Aug 5, 2025
Active trench digging is underway.
Pipe Installation
Aug 5, 2025
Pipes are visible laid within the trench.
Complete trenching to the full extent, finalize pipe installation, proceed with backfilling and surface restoration.
4/7/25
4/7/25
8/4/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/5/25
8/6/25
8/7/25
8/7/25
8/22/25
9/4/25
1/26/26