50%
completion
First
Mar 14, 2025
263 days
Last
Dec 2, 2025
The waterline construction project progressed from initial site marking to partial pipeline installation and trench formation by the end of the series. The site appears to be mid-project, with significant trenching and groundwork visible.
Start Condition
Snow-covered cracked pavement with a waterline marking.
Current Condition
Trench partially open near a building, with some debris and earthwork visible.
Excavation started
Apr 7, 2025
Trench excavation is visible, with trenching work in progress.
Pipe Installation
Aug 14, 2025
A green pipe segment is visible, indicating partial pipe installation.
Pipe Connection
Aug 28, 2025
A blue pipe with fittings is visible, indicating further pipeline progress.
Continue trenching and pipeline installation, then backfill and grade the area.
3/14/25
4/7/25
8/14/25
8/25/25
8/26/25
8/27/25
8/27/25
8/28/25
8/28/25
9/11/25
9/11/25
9/11/25
9/16/25
11/14/25
12/2/25
12/2/25