/FLORISTON FILTRATION PROJECT
3,076active
All Reports

16 photos at this spot

16 photos · 10 analyzed 39.39458, -120.02141 Mar 10, 2026 · 12:27 PM

50%

completion

First

Mar 14, 2025

263 days

Last

Dec 2, 2025

The waterline construction project progressed from initial site marking to partial pipeline installation and trench formation by the end of the series. The site appears to be mid-project, with significant trenching and groundwork visible.

Construction Milestones2 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

Snow-covered cracked pavement with a waterline marking.

Current Condition

Trench partially open near a building, with some debris and earthwork visible.

Timeline

Excavation started

Apr 7, 2025

Trench excavation is visible, with trenching work in progress.

Pipe Installation

Aug 14, 2025

A green pipe segment is visible, indicating partial pipe installation.

Pipe Connection

Aug 28, 2025

A blue pipe with fittings is visible, indicating further pipeline progress.

Work Types Observed

excavationpipeline installationtrenching

Next Steps

Continue trenching and pipeline installation, then backfill and grade the area.

Photos in this Report (16)

3/14/25

4/7/25

8/14/25

8/25/25

8/26/25

8/27/25

8/27/25

8/28/25

8/28/25

9/11/25

9/11/25

9/11/25

9/16/25

11/14/25

12/2/25

12/2/25