/FLORISTON FILTRATION PROJECT
3,076active
All Reports

20 photos at this spot

20 photos · 10 analyzed Mar 10, 2026 · 10:51 AM

85%

completion

First

May 27, 2025

86 days

Last

Aug 21, 2025

Over the course of 86 days, the site transitioned from initial excavation to the installation of new infrastructure, including trenching and pipe placement. The work area appears near completion with recent backfilling activity.

Construction Milestones5 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

Site with initial excavation revealing a portion of an existing pipeline.

Current Condition

Trench filled with visible blue piping and backfilled, with the surface restored to a maintained state.

Timeline

Initial Excavation

May 27, 2025

Ground broken with a section of pipeline exposed.

Trench Completion

May 28, 2025

Trench fully dug to appropriate grade.

Pipe Installation

Jul 14, 2025

Pipes visibly laid in the trench.

Backfill Completion

Jul 15, 2025

Trench filled back in with material.

Grading Finished

Jul 15, 2025

Final grade achieved with surface restored.

Work Types Observed

excavationtrenchingpipe installationbackfillinggrading

Next Steps

Final inspection and cleanup; ensure all markings and barriers are removed and the work area is safe for public access.

Photos in this Report (20)

5/27/25

5/27/25

5/28/25

5/28/25

7/8/25

7/14/25

7/14/25

7/14/25

7/15/25

7/15/25

8/1/25

8/1/25

8/20/25

8/20/25

8/20/25

8/20/25

8/20/25

8/20/25

8/21/25

8/21/25