/FLORISTON FILTRATION PROJECT
3,076active
All Reports

3 photos at this spot

3 photos · 3 analyzed Mar 10, 2026 · 10:51 AM

30%

completion

First

Apr 30, 2025

16 days

Last

May 16, 2025

Over the course of 16 days, significant excavation took place and major earth-moving operations were evident. The area progressed from an untouched or natural state to being prepped with machinery indicating active development.

Construction Milestones1 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

The site appears undisturbed with natural terrain, showing an early stage of excavation beginning.

Current Condition

The site shows clear signs of ongoing earth-moving activities with heavy machinery at work, indicating continued preparation and excavation.

Timeline

Excavation Started

Apr 30, 2025

Initial excavation and ground-breaking activities have begun.

Work Types Observed

excavationearth moving

Next Steps

Continue excavation and start trenching activities. Preparation for potential pipe installation or further site leveling may follow.

Photos in this Report (3)

4/30/25

5/7/25

5/16/25