100%
completion
First
Mar 14, 2025
241 days
Last
Nov 10, 2025
The construction site progressed from an initial undisturbed state to a completed water line installation with surface restoration. Key activities included excavation, pipe installation, and backfilling.
Start Condition
The site was undisturbed with a marked road indicating waterline plans.
Current Condition
The site is restored with visible surface elements indicating completed installation.
Initial Marking
Mar 14, 2025
Site marking for planned water line location
Excavation Started
Apr 7, 2025
Excavation of trench for water line
Trench Prepared
Aug 7, 2025
Trench completed and ready for pipe installation
Pipe Installation
Aug 7, 2025
Pipes laid in trench
Backfill Complete
Sep 5, 2025
Trench filled back in
Surface Grading
Sep 5, 2025
Surface graded, area leveled and compacted
Final Completion
Sep 8, 2025
Site restored, work completed
No further construction activities anticipated as work appears complete.
3/14/25
4/7/25
8/7/25
8/7/25
8/7/25
8/7/25
8/7/25
8/8/25
9/5/25
9/5/25
9/8/25
9/8/25
9/8/25
9/8/25
9/8/25
9/8/25
9/9/25
9/9/25
9/9/25
11/10/25