80%
completion
First
May 27, 2025
245 days
Last
Jan 27, 2026
The series of photos documents the excavation and installation of piping in a roadway, followed by trench backfilling and site restoration. The site progresses from initial excavation to final grading and surface restoration.
Start Condition
Initial excavation site with measurement being taken of the excavation depth.
Current Condition
Site appears graded and restored, with workers performing finishing activities on the roadway surface.
Initial Excavation
May 27, 2025
Depth of excavation being measured at initial stage.
Trench Completion
Jul 15, 2025
Trench fully dug to required depth and length.
Pipe Installation
Jul 28, 2025
Pipe observed installed within the trench.
Backfill Completion
Aug 4, 2025
Trench appears filled back in with earth.
Grading Finished
Aug 5, 2025
Final grading and site leveling in progress.
Final surface treatment and paving to be completed, followed by site cleanup.
5/27/25
5/27/25
7/15/25
7/28/25
8/4/25
8/4/25
8/4/25
8/4/25
8/5/25
8/21/25
8/21/25
1/26/26
1/26/26
1/26/26
1/26/26
1/27/26
1/27/26
1/27/26
1/27/26
1/27/26