/FLORISTON FILTRATION PROJECT
3,076active
All Reports

20 photos at this spot

20 photos · 10 analyzed Mar 10, 2026 · 10:09 AM

80%

completion

First

May 27, 2025

245 days

Last

Jan 27, 2026

The series of photos documents the excavation and installation of piping in a roadway, followed by trench backfilling and site restoration. The site progresses from initial excavation to final grading and surface restoration.

Construction Milestones5 / 6 detected

Excavation
Trench Completion
Pipe Installed
Backfill Complete
Concrete Poured
Grading Finished

Start Condition

Initial excavation site with measurement being taken of the excavation depth.

Current Condition

Site appears graded and restored, with workers performing finishing activities on the roadway surface.

Timeline

Initial Excavation

May 27, 2025

Depth of excavation being measured at initial stage.

Trench Completion

Jul 15, 2025

Trench fully dug to required depth and length.

Pipe Installation

Jul 28, 2025

Pipe observed installed within the trench.

Backfill Completion

Aug 4, 2025

Trench appears filled back in with earth.

Grading Finished

Aug 5, 2025

Final grading and site leveling in progress.

Work Types Observed

excavationtrenchingpipe installationbackfillinggrading

Next Steps

Final surface treatment and paving to be completed, followed by site cleanup.

Photos in this Report (20)

5/27/25

5/27/25

7/15/25

7/28/25

8/4/25

8/4/25

8/4/25

8/4/25

8/5/25

8/21/25

8/21/25

1/26/26

1/26/26

1/26/26

1/26/26

1/27/26

1/27/26

1/27/26

1/27/26

1/27/26