No caption
IMG_6896.JPG
Details
Wednesday, March 26, 2025 · 4:00 PM
39.39144, -120.02109· 1680m
Location Context
1 / 5
USGS Topo
No elevation data
FEMA Flood
No flood data
OSM Infra
No address data
USDA Soil
No soil data
USGS Hydro
No hydro data
Apple iPhone 16 Pro
iPhone 16 Pro back triple camera 2.22mm f/2.2
2.220000028611935mmf/2.21/585sISO 50
Flash did not fire, compulsory flash mode
Show all EXIF (43 fields)
ApertureValue2.2750
BrightnessValue8.4031
ColorSpace65535
CompositeImageGeneral Composite Image
ExifImageHeight3024
ExifVersion2.3.2
ExposureCompensation0
ExposureModeAuto
ExposureProgramNormal program
FlashpixVersion1.0
FocalLengthIn35mmFormat14
GPSDateStamp2025:03:26
GPSDestBearing244.5659
GPSDestBearingRefTrue North
GPSHPositioningError2.8651
GPSImgDirection244.5659
GPSImgDirectionRefT
GPSSpeed0.1712
GPSSpeedRefK
GPSTimeStamp23:0:3
HostComputeriPhone 16 Pro
latitude39.3914
LensInfo2.2200, 15.6600, 1.7800, 2.8000
LensMakeApple
longitude-120.0211
MeteringModePattern
ModifyDate2025-03-26T16:00:03.000Z
OffsetTime-07:00
OffsetTimeDigitized-07:00
OffsetTimeOriginal-07:00
ResolutionUnitinches
SceneCaptureTypeStandard
SceneTypeDirectly photographed
SensingMethodOne-chip color area sensor
ShutterSpeedValue9.1918
Software18.4
SubjectArea{"0":2000,"1":1511,"2":2217,"3":1330}
SubSecTimeDigitized954
SubSecTimeOriginal954
WhiteBalanceAuto
XResolution72
YCbCrPositioning1
YResolution72
AI Analysis
Wooden formwork is constructed in a circular pattern for a tank foundation at the center of the image. Multiple excavators and construction vehicles are visible in the background. The area is surrounded by mountains and trees, suggesting a remote or mountainous location. Soil appears to be excavated around the foundation structure.
rebar-formwork
excavated soil partly cloudy with natural daylight open site with apparent ample space for equipment
Safety features like PPE and controls are not visible in frame.
Equipment & Materials
Analyzed Apr 21, 2026
Nearby Photos
1m
excavation
excavationfoundation-prep
excavator
1m
excavation
excavationfoundation-excavation
excavator
1m
mechanical installation
tank-maintenancematerial-handling
crane
1m
mechanical installation
tank-setupequipment-operation
boom-lift
2m
concrete work
tank-foundation-constructionfoundation-work
backhoe
2m
concrete work
concrete-pouringformwork-setup
concrete mixer truck
3m
concrete work
seam-sealingconcrete-sealing
sealant
3m
excavation
excavation-worktank-foundation-excavation
large excavator
3m
excavation
excavationearthmoving
CAT 335F excavator
3m
excavation
excavationfoundation-preparation
excavator